
The information contained within this announcement is deemed to constitute inside information as stipulated under the retained EU law version of the Market Abuse Regulation (EU) No. 596/2014 (the "
("
Ironveld PLC Signs Mining Operations Agreement
Agreement provides for a
Under the Agreement, Daemaneng will assume full responsibility for all mining operations at the Lapon site - including all capital investment, operating costs, logistics, labour, compliance, and the establishment of on-site processing infrastructure - thereby eliminating any future mining-related expenditure for Lapon Mining.
The arrangement effectively transfers operating and funding obligations to Daemaneng, de-risking
Based on currently anticipated production levels, Daemaneng is expected to fund approximately
No equity participation or ownership interest in Lapon Mining or any other
Key Highlights
·
The Agreement transfers all mining-related operating and capital expenditure to Daemaneng, enabling
· Three-Year Term and Five-Year Exclusivity:
The Agreement provides for an initial three-year operational term, with Daemaneng expected to fund approximately
The Contractor has been granted exclusive operating rights for five years, conditional upon maintaining full compliance with all agreed investment, production, and performance obligations. All ore supply and marketing activities will be conducted on a transparent, open-book basis, ensuring complete accountability, governance oversight, and alignment of interests between the parties.
· Guaranteed Ore Supply to the JV DMS Plant:
Daemaneng is contractually obligated to supply all ore required by
· New and Additional Revenue Stream:
The partnership establishes an additional and strategically valuable income channel through the commercialisation of Run-of-Mine ("ROM") material, complementing
· Commencement of Operations and Proven
Mining operations under Daemaneng will commence shortly, with Daemaneng now fully responsible for achieving all production volumes and quality standards in line with market requirements, contractual obligations, and agreed performance parameters. Having successfully mined material from Lapon in 2018, Daemaneng brings proven operational familiarity with the deposit and its infrastructure, positioning the project for immediate mobilisation, efficient execution, and scalable growth.
Commenting on the Agreement,
"This agreement marks a defining moment in
"The partnership with Daemaneng establishes a performance-based framework that is mutually beneficial and commercially aligned. Its structure ensures that mining costs are minimised to maximise profitability, Daemaneng's upside is driven entirely by operating efficiently, mining cost-effectively, and marketing material at the most competitive prices.
"By engaging an established and operationally experienced partner, we are unlocking immediate production at Lapon without further capital outlay. The agreement removes the majority of mining-related expenditure from our balance sheet while introducing a new revenue stream through ROM sales, enabling
"Daemaneng's familiarity with the Lapon site, combined with their investment commitment and established offtake channels, gives us confidence that operations will ramp up rapidly and profitably. With no opex or capex commitments in mining,
About
Next Steps
Mining operations at Lapon will shortly transition to the management of Daemaneng, who will assume full operational responsibility and mobilise its own mining fleet, equipment, and personnel to site. This change will enable the release of all previously contracted equipment and service providers, thereby removing related monthly costs from Lapon's accounts.
Production and first ore deliveries to the DMS plant under Daemaneng are targeted within the next 30 days. In parallel, initial ROM sales to offtakers are anticipated to begin, further enhancing near-term cash flow generation.
Update on JV DMS Plant Operations
A move in this direction would be fully aligned with
Discussions and negotiations are ongoing and progressing positively, with both parties confident that a mutually acceptable agreement for a Plant Operator Agreement will be reached in the very near term, which should enable and facilitate a natural transition towards the finalisation of the broader JV agreement with
Operational Progress Update
DMS Plant Progress
Construction of the DMS plant was completed in
During commissioning, throughput was progressively increased as the steel ball load in the mill was optimised. The plant successfully achieved targeted tonnage rates and consistently produced magnetite that met the required magnetic content specifications. Minor refinements to product moisture and sizing have been completed, and attention is now focused on optimising water recovery and recirculation systems to support continuous operations.
Mining Progress
Mining activities have advanced in parallel. The initial open-pit overburden strip of approximately 250 metres was completed in May, yielding around 2,000 tonnes of weathered magnetite ore for plant commissioning. In June, the first waste blast across a 30-metre strike length was executed successfully, and by late July, approximately 4,000 tonnes of fresh magnetite ore were blasted and delivered to the DMS plant for the final stages of commissioning and separator calibration.
Sales and Market Engagement
Initial trial production samples have been delivered to prospective offtake partners, who provided positive feedback while identifying certain process adjustments to further align production with specific requirements. These adjustments have now been implemented.
Tender and Market Update
Regarding the tender process for the supply of DMS-grade magnetite previously communicated, the Company can report that, following correspondence received in
Feedback has been constructive and positive, noting satisfaction with the quality of magnetite samples supplied during trial production. The communication also confirmed continued interest in establishing a long-term supply relationship, with the plants' logistical advantage and proximity to key industrial users identified as important differentiating factors.
While the reasons for the delay in awarding the tender have not been communicated, we have no reason to believe anything other than that we remain well positioned within the process.
Beyond this process, the addressable market for DMS-grade magnetite in
Outlook
Together with the Mining Operations Agreement announced today and the DMS Joint Venture discussions with
For further information, please contact:
|
|
c/o BlytheRay +44 20 7138 3204
|
Cavendish
|
|
+44 20 7220 0500 |
|
|
+44 20 3657 0050 |
BlytheRay |
|
+44 20 7138 3204 |
RNS may use your IP address to confirm compliance with the terms and conditions, to analyse how you engage with the information contained in this communication, and to share such analysis on an anonymised basis with others as part of our commercial services. For further information about how RNS and the