
Kore Potash Plc
("
Finalisation of EPC Contract
Upon the release of this announcement on the Australian Securities Exchange ("ASX") and the JSE Limited ("JSE"), the ASX suspension and the JSE halt of trading in the securities of
Highlights:
· The EPC is a fixed-price contract, with a price of
o The fixed price element is critical in that it minimises the cost overrun risks to the Company.
o Of the total
· Construction period is 43 months
o The EPC includes provisions for penalties in the event of delayed completion and bonuses in the event of early completion as detailed further below.
· Entry into the EPC reaffirms the Board's aim for
· While the signing of the EPC represents a significant milestone for the Company, the Company notes that there is still a significant number of major milestones that need to be satisfied before the commencement of first production at the
Risk mitigation, contract terms and other arrangements with
· The most significant risks that
o Capital cost overruns
o Time to completion overruns
o Achievement of product quality specifications for our target markets
o Operator risk
·
· The EPC has a total fixed price offer amount of
· Given the evidence of cost overruns in the mining industry (a McKinsey report published in 2017 notes that as many as four out of five mining projects are completed late and over budget by an average of 43%)[3], a fixed-price contract represents a significant reduction in the risk of cost overruns and provides greater financial certainty to both
· The scheduled construction time for the
o The Contract includes provisions for delay penalties should construction exceed the timeline. In the unlikely event that the construction period runs over by 270 days,
o The EPC allows for an extension of the completion timeline (not cost) if the geotechnical conditions differ significantly from what was identified during the various drilling programmes and seismic surveys.
· Under the EPC, the final completion test requires a level of production that fully complies with the MoP specifications normally supplied to the Brazilian market, which are as follows:
Red Granular Muriate of Potash ("MoP") specification
Chemical Analysis |
|
|
|
|
|
Chemical Composition |
Unit |
Requirement |
|
|
|
Potassium Oxide, as K2O |
% |
≥60 |
Potassium Chloride, as KCl |
% |
≥95 |
Moisture, as H2O |
% |
<0.2 |
|
|
|
Other Properties |
|
|
|
|
|
Size Guide Number (SGN) |
- |
≥310 |
Uniformity Index |
- |
≥50 |
Colour |
|
Pink/Red |
· One of
·
· To accelerate progress during the financing process,
·
EPC and the
· The EPC is a fixed price contract worth
· Entry into the EPC reaffirms the board's aim for
·
· Kola has been designed with a nameplate production capacity of 2.2 million tonnes per annum of MoP as indicated in the Kola Definitive Feasibility Study ("DFS").[7]
· MoP production from Kola is scheduled over a 33-year life of mine as indicated in the DFS.[8]
· As indicated in the DFS, Kola is a conventional mechanised underground potash mine with shallow shaft access, making it globally one of the lowest cost projects. Ore from underground is transported to the processing plant via an approximately 25.5 km long overland conveyor[9]. After processing, the finished product is conveyed 8.5 km to the marine export facility[10]. MoP is transferred from the storage area onto barges via a dedicated barge loading jetty before being transhipped into ocean-going vessels for export[11]. The granular MoP produced by Kola meets a minimum quality of 95.0% KCl in accordance with international standards.
Financing
· The EPC remains subject to Financial Close.
· As announced on
· In line with this memorandum of understanding, following signing the EPC, Summit is expected to deliver a non-binding financing term sheet within three months. This term sheet will be subject to the completion of detailed and definitive legal documentation.
· The Company confirms its confidence in the
· The material terms of the Summit MOU were set out in the
o The Summit MOU outlines a roadmap to optimise the capital design to fully finance and construct Kola via a mix of debt and royalty financing.
o Under the proposed financing arrangements, the ROC Government will retain their 10% shareholding in Kola.
o Under the Summit's proposed financing structure, the Company will not contribute to the capital needed to build the
· The Company retains the right not to accept any finance proposal presented by Summit and there is no guarantee that any proposal or legally binding agreement will be forthcoming. The Company provides no assurance to shareholders that the
· The Company expects any financing provided by the
· The Company confirms the
· Further details about the financing arrangements will be notified to the market in accordance with the Company's continuous disclosure obligations.
Targeted timeline
While the signing of the EPC represents a significant milestone for the Company, the Company notes that there is still a significant number of major milestones that need to be satisfied before the commencement of first production at the
The indicative timeline of these major milestones to first production from
· End of
· End of
· Second half of 2025:
o Financial Close under the EPC.
o FNTP issued under the EPC.
o Commencement of construction under the EPC.
· First half of 2029 - first production at the
The Company will notify the market of any material variations to this timeline in accordance with its continuous disclosure obligations.
"The entry into this EPC contract marks a significant milestone for the Kola potash project. By signing this fixed-price construction contract with one of the largest international engineering groups, the Company has minimized risks associated with cost and time overruns typical in large mining projects. The Company also believes this structure will facilitate accelerated financing and a relatively straightforward construction process, leading us to profitable production.
We now look forward to working with all our stakeholders in taking this world-class mining project to the next level and unlocking its full potential, in accordance with the indicative timeline described above.
I would like to take this opportunity to thank the Government of the
EPC Summary Details
The Company confirms that no counterparty to the EPC is a related party of the Company.
Early Works Agreements
The EPC includes an Early Works Agreement with
· Supplementary geological surveys, which shall consist of drilling at the shaft works and marine works locations;
· Final FEED design relating to the shaft works; and
· Beneficiation Testing to validate the test results completed during the DFS.
This will be carried out before the FNTP is issued.
The Beneficiation Testing includes
Additional Payments to Power China
As announced on 8 August 2023[15],
As previously disclosed by the Company, two payments of
Summary of EPC fixed price contract
Overview of EPC
The EPC is an agreement between
Breakdown of Contract Price
|
|
Description |
Amount (US$ million) |
|
|
Underground Works (shafts and mine face preparation) |
319.7 |
Processing plant and auxiliary facilities |
609.6 |
Surface over land belt conveyor transportation (OLC)* |
229.3 |
|
|
Marine Works* |
223.1 |
Roads* |
111.3 |
Utilities (electricity overhead line & gas pipeline)* |
145.2 |
Administration facilities |
58.9 |
General items |
231.9 |
|
|
Total |
1,929.0 |
* Total
Contract Price
The EPC between
The Contract Price may be amended only under limited scenarios as outlined below:
· If the FNTP is not issued by the FNTP Longstop Date (outlined below) and this is not due to any fault of the Contractor, the Contractor may request adjustments to the Contract Price. If
· If the Contractor incurs costs due to
· If
· The Contract Price can be adjusted if costs increase or decrease due to changes in the laws of the ROC (including the introduction of new laws and the repeal or modification of existing laws). Both parties must agree to the price adjustment.
· If
· Regarding the Early Works Agreement, if the results of the Beneficiation Test differ from the DFS tests, there may be a variation to the scope of works.
Timing for payment of Contract Price
Under the EPC (and as is customary for a contract of this scale and nature), the total Contract Price of
FNTP / Commencement Date
The EPC does not require a limited notice to proceed.
The FNTP Long Stop date is 12 months after the completion of the Early Works, or as may be extended by agreement of both parties. If the FNTP has not been issued within this period, the Contractor has the right to request a change in the Contract Price, which
Duration of EPC
Under the EPC, the scheduled "Take Over Date" for the project is 43 months from the commencement date of the Contract.
The only basis on which the 43 month period can be extended is if any significant errors, inaccuracies, or discrepancies are found in the DFS geotechnical information provided to
Should the Scheduled Take Over Date be delayed, then
· Month 1: 0.010% per day /
· Month 2-3: 0.015% per day /
· Months 4 and after: 0.02% per day /
If the works are completed prior to the Scheduled Take Over Date by
· Month 1: 0.010% per day /
· Month 2-3: 0.015% per day /
· Months 4-5: 0.02% per day /
Any bonus which
If the work carried out under the EPC does not pass the last Test on Completion, within 270 days of the Scheduled Take Over Date then
Completion Test / performance levels
The Minimum Performance Guarantee Level is 95% of the volume performance target for each parameter, based on 100% of the product specifications.
If
If the performance level is greater than the Minimum Performance Level but less than the designed production capacity of 2.2 million tonnes,
If
If there is a defect or damage that deprives
Non-buildability
Since the EPC is a fixed-price contract, a non-buildability clause is included. Under the Contract,
Obligations on Company
The EPC contains various obligations on the Company that are customary for a contract of this scale and nature. This includes obligations on the Company to provide
Failure of EPC
As at the date of this announcement, the Company has not considered any alternative options for developing the
Risks
Key project and technical risks identified to the
· Ability to secure project funding.
· Global potash price change.
· Material changes to either capital or operational costs.
· Development of market and sales agreements for MoP.
· Geotechnical and geological design parameters not accurately predicting rock mass conditions and nature of orebody.
· Hydrogeological design parameters do not adequately control water influx.
· Conversion of MoUs for energy supply (electricity and gas) into commercial contracts.
· Changes in the mining convention.
· RoC political risk.
· Changing community or local government expectations.
· Exchange rates.
Forward-Looking Statements
This release contains certain statements that are "forward-looking" with respect to the financial condition, results of operations, projects and business of the Company and certain plans and objectives of the management of the Company. Forward-looking statements include those containing words such as: "anticipate", "believe", "expect," "forecast", "potential", "intends," "estimate," "will", "plan", "could", "may", "project", "target", "likely" and similar expressions identify forward-looking statements. By their very nature forward-looking statements are subject to known and unknown risks and uncertainties and other factors which are subject to change without notice and may involve significant elements of subjective judgement and assumptions as to future events which may or may not be correct, which may cause the Company's actual results, performance or achievements, to differ materially from those expressed or implied in any of our forward-looking statements, which are not guarantees of future performance.
Neither the Company, nor any other person, gives any representation, warranty, assurance or guarantee that the occurrence of the events expressed or implied in any forward-looking statement will actually occur. Except as required by law, and only to the extent so required, none of the Company, its subsidiaries or its or their directors, officers, employees, advisors or agents or any other person shall in any way be liable to any person or body for any loss, claim, demand, damages, costs or expenses of whatever nature arising in any way out of, or in connection with, the information contained in this document.
In particular, statements in this release regarding the Company's business or proposed business, which are not historical facts, are "forward-looking" statements that involve risks and uncertainties, such as Mineral Resource estimates market prices of potash, capital and operating costs, changes in project parameters as plans continue to be evaluated, continued availability of capital and financing and general economic, market or business conditions, and statements that describe the Company's future plans, objectives or goals, including words to the effect that the Company or management expects a stated condition or result to occur. Since forward-looking statements address future events and conditions, by their very nature, they involve inherent risks and uncertainties. Actual results in each
case could differ materially from those currently anticipated in such statements. Shareholders are cautioned not to place undue reliance on forward-looking statements, which speak only as of the date they are made. The forward-looking statements are based on information available to the Company as at the date of this release. Except as required by law or regulation (including the ASX Listing Rules), the Company is under no obligation to provide any additional or updated information whether as a result of new information, future events or results or otherwise.
Market Abuse Regulation
Market Abuse Regulation (MAR) Disclosure The information contained within this announcement is deemed by the Company to constitute inside information as stipulated under the Market Abuse Regulations (EU) No. 596/2014 which has been incorporated into
This announcement has been approved for release by the Board.
For further information, please visit www.korepotash.com or contact:
Kore Potash
|
Tel: +44 (0) 20 3963 1776 |
Tavistock Communications |
Tel: +44 (0) 20 7920 3150 |
SP Angel Corporate Finance - Nomad and Joint Broker Charlie Bouverat |
Tel: +44 (0) 20 7470 0470 |
Shore Capital - Joint Broker James Thomas |
Tel: +44 (0) 20 7408 4050 |
Questco Corporate Advisory - JSE Sponsor Doné Hattingh |
Tel: +27 63 482 3802 |
[1]
[2] The Contract Price remains fixed, subject to certain adjustments in limited circumstances as specified in detail below.
[3] McKinsey Report dated
[4] See below under the heading "Timing for payment of Contract Price" for further information regarding the payment of the EPC Contract Price, including the
[5]
[6] Figures calculated per the Company's internal modelling and estimates as at
[7]
[8] Ibid.
[9] Ibid.
[10] Ibid.
[11] Ibid.
[12]
[13] Ibid.
[14] See below under the heading "Timing for payment of Contract Price" for further information regarding the payment of the EPC Contract Price.
[15]
RNS may use your IP address to confirm compliance with the terms and conditions, to analyse how you engage with the information contained in this communication, and to share such analysis on an anonymised basis with others as part of our commercial services. For further information about how RNS and the