• Repairs and scheduled maintenance work on the Triton FPSO have been completed, and the restart process for production operations is now underway.
• This is consistent with the management’s indicated timing of “around end of June” as stated in the AGM update.
• Production is expected to ramp up progressively, reaching steady-state levels later in July.
• No further shutdowns are planned for Triton in 2025. We continue to anticipate 2H25 production in the range of 41–47 mboe/d. Before shutdown, ....

30 Jun 2025
Serica Energy Plc (AIM: SQZ): Start up at Triton in line with expectations

Sign up to access
Get access to our full offering from over 30 providers
Get access to our full offering from over 30 providers
Serica Energy Plc (AIM: SQZ): Start up at Triton in line with expectations
Serica Energy PLC (SQZ:LON) | 164 -7.6 (-2.7%) | Mkt Cap: 645.3m
- Published:
30 Jun 2025 -
Author:
Stephane Foucaud -
Pages:
5 -
• Repairs and scheduled maintenance work on the Triton FPSO have been completed, and the restart process for production operations is now underway.
• This is consistent with the management’s indicated timing of “around end of June” as stated in the AGM update.
• Production is expected to ramp up progressively, reaching steady-state levels later in July.
• No further shutdowns are planned for Triton in 2025. We continue to anticipate 2H25 production in the range of 41–47 mboe/d. Before shutdown, ....