18 Feb 2025
Serica Energy Plc (AIM: SQZ): Triton shut down until March: frustrating but unlikely to be too impactful
• Production at Triton has been suspended due to issues caused by Storm Éowyn, which resulted in minor damage to one of the cargo tanks. While preparing to conduct repairs, an integrity issue with a coupling in the inert gas line required for purging the tanks was identified. The FPSO remains offline pending identification of the root cause.
• Production is now expected to restart in mid to late March, but the summer maintenance shutdown could also be longer than the expected 40 days as further ....

Sign up to access
Get access to our full offering from over 30 providers
Get access to our full offering from over 30 providers
Serica Energy Plc (AIM: SQZ): Triton shut down until March: frustrating but unlikely to be too impactful
Serica Energy PLC (SQZ:LON) | 127 -14.4 (-8.2%) | Mkt Cap: 497.2m
- Published:
18 Feb 2025 -
Author:
Stephane Foucaud -
Pages:
5 -
• Production at Triton has been suspended due to issues caused by Storm Éowyn, which resulted in minor damage to one of the cargo tanks. While preparing to conduct repairs, an integrity issue with a coupling in the inert gas line required for purging the tanks was identified. The FPSO remains offline pending identification of the root cause.
• Production is now expected to restart in mid to late March, but the summer maintenance shutdown could also be longer than the expected 40 days as further ....