• The contract for the construction of a new 21 km gas pipeline (previously 14 km) for the SE‑MGH 5–7 mmcf/d development was signed in early January. Site preparation is already underway, with first gas expected in 2Q26.
• Project capex is now estimated at US$2 mm (vs. prior guidance of US$2–3 mm), of which US$1.9 mm has already been incurred. The subsequent North MGH phase—requiring ~US$1 mm of incremental capex—would lift total production to 7–10 mmcf/d.
• The company has agreed key commercial ....
10 Feb 2026
Criterium Energy Ltd (TSX-V: CEQ): First Gas in 2Q26 with a Likely Upgrade to Discovered Gas Resources
Sign up to access
Get access to our full offering from over 100 providers
Get access to our full offering from over 100 providers
Criterium Energy Ltd (TSX-V: CEQ): First Gas in 2Q26 with a Likely Upgrade to Discovered Gas Resources
• The contract for the construction of a new 21 km gas pipeline (previously 14 km) for the SE‑MGH 5–7 mmcf/d development was signed in early January. Site preparation is already underway, with first gas expected in 2Q26.
• Project capex is now estimated at US$2 mm (vs. prior guidance of US$2–3 mm), of which US$1.9 mm has already been incurred. The subsequent North MGH phase—requiring ~US$1 mm of incremental capex—would lift total production to 7–10 mmcf/d.
• The company has agreed key commercial ....